The subject of the in progress contract is investor's supervision along with the construction administration on the construction project of two wind farms located in the Wielkopolskie voivodship, ie: Gościejewo and Rawicz. We provide services during the stage of construction works (construction of foundations, roads and squares as well as cable works) as well as the assembly stage of turbines delivered by Vestas along with start-up. Commissioning of the farms is planned for the third quarter of 2022.
Characteristics of the wind farms:
3 Vestas V 110 turbines 2 MW each
Hub Height 125 m
foundation diameter 17.7 meters
1 Vestas V 100 turbine with a capacity of 2 MW
Hub Height 120 m
foundation diameter 20 meters
both investment projects run in parallel