The subject of the contract was project management with the investors supervision during the assembly and commissioning of the 1.06 MW photovoltaic installation. The installation was assembled on the structure of the new warehouse building DAMCO in Mszczonów.
Characteristics of the object:
JA Solar JAM72-450MR
2 394
BAKS DP-DNHBE-WZ
SolarEdge SE 82.8K + SolarEdge 50-100kW inverters auxiliary unit
8
SolarEdge P950
KBE 4mm2
MC4 serial MultiContact
Project management, comprehensive investor supervision during delivery, at the stage of installation on the roof and during commissioning.
This installation is an "off-grid" photovoltaic installation and was not connected to the power grid at the end of the investment. The energy produced from the photovoltaic installation is fully used for the own needs of the newly established and existing facility. Solar panels on the roof face east and west. Power production expected at the level of 953.2 MWh / year.
Damco Poland Sp. z o.o.
Wszelkie prawa zastrzeżone KKBud Sp. z o.o.
Wykonane przez: Empressia
All rights reserved by KKBud Sp. z o.o.
Realization: Empressia