The subject of the Agreement was the function of the Construction Manager in the process of preparing and executing the investment project of the SELGROS Warszawa – Piaseczno shopping center building at Kuropatwy and Puławska Street. The project was implemented in the form of “Construction Management” in the period of preparation, design before construction and during construction.
Characteristics of the object:
Building:
Sales hall for sale of finished goods
Construction:
One-storey wholesale hall with warehouse and auxiliary function, part of two-level hall for administration, social and technical rooms.
Usable area:
15 382 m²
Building area:
13 207 m²
Total height:
10,75 m
Additionally:
reconstruction of the external road system Kuropatwy/Puławska Street
Additionally:
in the hall was designed the Horeca area for wholesale catering supplies. In the main sales hall there is also a presentation point – a place for the organization of shows, promotions and tastings.
Selgros Cash&Carry
Scope of work
Stahe I – Investor’s interests in the course of work related to the development of the Local Spatial Management Plan; preparation of a preliminary schedule for implementation of design and construction work; coordination, verification and supervision of the process of obtaining technical specifications for powering in the media; coordination of activities related to obtaining all the formal and legal documents required by law in the aspect of the proper communication of the plot.
Stage II – developing descriptions of works including measurements, i.a.: control of the completeness and quality of LVs in the scope of detailed description of the conditions of execution and acceptance of construction works.
Stage III – tenders, including: preparation of tendering procedure; analysis of offers; participation in the negotiations with a recommendation of choice.
Stage IV – site management, construction management including investor’s supervision, geotechnical supervision, coordination of external works.